SMHG — Spruce Grove Manor · 3D Construction & Equipment Simulation

260 Pioneer Road, Spruce Grove, AB · CSTN 2370 · Simulation & Estimate Model (Structure Design per S2 / Protostatix Permit Drawings)

Simulation by: Jievy Tabiolo
1. Simulation Timeline Phases
2. Crew Handling & Equipment Simulation
Simulated Date
Sep 02, 2026
Working Day 1 / 210
Cumulative Concrete
0 m³
5,774.74 m³ total (incl. overrun)
Earned Direct Cost
$0
of $3,116,096 unburdened
Active Site Crew
7 workers
Drilling & cage rigging
Item / RateRate UsedSource Document
Piling Crew Labour
Foreman / Drill Op / Loader Op / Lab
$76.00 / $70.50 /
$40.60 / $26.50 /hr
Initial Instr. §1a
Unburdened hourly rates
Piling Productivity
Shaft + 60° Bell (2 rigs)
0.0284 crew-hr/ft +
3.0 / 3.375 / 3.75 hr
Initial Instr. §1 &
Memo #1 R2
Rebar Cages & Dowels
Tied cages + 20M/15M dowels
$450/pile cage;
$2.50/kg (assumed)
Memo #1 R2 &
S1.02 Note 15
Geotech & Tailings
Continuous insp. + export
$138.00/hr insp.;
$6.55/Lm³ export
Initial Instr. §1, §1b
Subcontract items
Div 3 Blended Crews
Formwork Carp / Concrete Place
$42.56/hr carp;
$38.75/hr placing
Memo #2 (2026)
Unburdened blended rates
Ready-Mix Concrete
S-2 / N / C-1 + Winter Heat
$275 / $265 / $285/m³;
+$45/m³ Nov 1–Apr 30
Initial Instr. §8 &
S1.02 Schedule
Concrete Pumping
38m, 42m, 47m, 52m booms
$190–$350/hr + $4–$6/m³
+$9.50/hr CO₂ + 14% sur.
Noremac 2023 Quote &
Memo #2 §9a ($250/m³ waste)
Flatwork Place & Finish
SOG & Suspended Slabs
$23.50/m³ SOG;
$19.78/m³ Susp.
Odie's Concrete Quote
(Sep 2 — sub-trade)
Formwork Materials
Ply, 2×4, collars, joists, tables
$68.50/$67 ply; $325/MBF;
$35/mo collar; $135/mo truss
Initial Instr. §2,
Memo #2, #3, #4
Rebar S/I, Burden & TC
Memo #3 Scope Additions
$2,890,750 rebar LS;
55% burden; $28,700/mo TC
Memo #3 (2026)
Added below sub-totals
Access & Rig Matting
80 road mats + 39 rig mats
$1.75/day road mat;
$15.00/day rig mat
TerraPro Q8694 &
Site Matting Brief
Equipment & SpecQty / DurationRate & Fuel/Maint
2× Soilmec SR-55 Drill Rigs
Ø500/Ø600 shafts + 60° bells
837.89 rig-hrs
(42 prod days)
$275.00/hr · 250 L/rig/day
Maint: 12% mach-hr ($350/hr)
Rig Lowbed Trucking
2 rigs × mob in + demob out
4 one-way moves $3,500.00 / move
($14,000 total)
Articulated Wheel Loader
2–3 LCU bucket (replaces 2 SSL)
460 hrs
(46 days incl. mobe)
$165.00/hr (AHRCA est.)
85 L/day · Maint: 6%
Piling Crew Truck
Full piling duration
46 working days $85.00/day · 100 L/week
Maint: 4% mach-hr
Piling Hand Tools & Tremie
Vibrators, drop chute, hoppers
42 prod days $65.00 / day
($2,730 total)
Tower Crane + Placing Bucket
56m jib, 25-person crew cap
~8 mos (Oct 27–
Jun 30, 2027)
$28,700/mo (Memo #3)
Bucket: 50–70 m³/hr
Noremac Boom Pumps
38m (13×), 42m (14×), 47m (4×), 52m (4×)
35 callouts
(159.15 pump hrs)
$210–$350/hr + $5/m³ avg
+$9.50/hr CO₂ + 14% sur.
Structure Small Tools
Vibrators, concrete bucket allow.
180 working days $120.00 / day
($21,600 total)
TerraPro Site Matting
80× 8'×14' 3-ply + 39× 8'×20' rig
240 rental days
+ install/trucking
$174k rent + $21.3k ops
($195,330 + tax)
BOXX Site Trailers (Ref.)
12×40 office, 12×60 lunch, 12×32 lav
Example Q-69087
(confirm duration)
$5,378/mo equipped
+$7,805 transp./clean
ScopeLabourMat/Eq/SubTotal
Drilled CIP Piles (184)$134,570$809,019$943,589
Div 3 Structure (Base)$298,617$1,873,890$2,172,507
Base Direct Subtotal$433,187$2,682,909$3,116,096
ItemCalculationAmount
Rebar Supply & InstallMemo #3 Lump Sum$2,890,750
Labour Burden (55%)55% × $433,187.36$238,253
Tower Crane (~8 mos)8 mos × $28,700/mo$229,600
TerraPro Site MattingQuote Q8694$195,330
Combined w/ Memo #3Incl. Rebar/TC/Burden$6,670,029
Pile Casing (25% / 50%)633.3m / 1,266.5m$69,659 / $139,318
Pile Casing (80% / 100%)2,026.4m / 2,533.1m$222,908 / $278,636
Scope & RFI Note: Building design is from the SMHG permit drawing set (S2 Architecture / Protostatix); this 3D simulation & cost model was built by Jievy Tabiolo. 184 unique piles carried (194 sensitivity = $994,871); 96 untyped column spots flagged for instructor confirmation.
1. Mobilization, Matting & Drilled CIP Piles 0% Complete
SAMPLE ONLY — This estimation is not accurate. This is only a sample, for study purposes.